150 kV Transmission Line in Kafireas, Evia
Requirements
Installed in the Municipality of Karystos, Evia, this complex is the largest wind farm in Greece, consisting of 7 wind farms with a total installed power of 154 MW.
Client
ΤERNA
gekterna.com2 km
150kV Overhead Transmission Line (special design)
The Challenge
Due to the high wind pressure in the area, studies had to be carried out regarding the wind load on the overhead line, as well as regarding the line’s mechanical strength.
The Solution
The results of the measurements indicated high stress on the lattices of the line, which led us to select pylons of higher mechanical strength.
Related Services
- Preliminary design of an overhead line for approval by IPTO
- Final Design of an overhead line to be approved by IPTO
Using the Final Design, the customer will construct an overhead line that will be able to withstand the adverse weather conditions of southern Evia.
Starting Date
April 2020
Project Completion
December 2021
Industry
Power plant development companies